Big changes are coming to ACC’s Round Rock Campus! The new Student Support Center is nearly complete and is set to open soon. The space is bringing together services like the Welcome Center, Career Center, Veterans Affairs, Advising, and Admissions in one easy-to-access location.
Construction is about 75% complete, with final touches like paint, flooring, and ceiling installation happening throughout October. The building is expected to reach substantial completion by late October or early November.
This project is funded through ACC’s Maintenance and Operations Bond, which also supports other campus improvements.
This isn’t the only project underway at the Round Rock Campus. To learn more about the Applied Technology Expansion at the Round Rock Campus, visit austincc.edu/bond.